slava.energy: UK renewable energy projects
Midland Quarry Products, Smith Road - Battery Storage
REPD record 14747. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 10 MW
- Status
- Planning Permission Granted
- Operator
- Gresham House Devco Pipeline Limited
- County
- West Midlands
- Region
- West Midlands
- Country
- England
- Planning authority
- Sandwell
- Planning reference
- DC/24/69271
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-02-25
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-05-02: Planning Application Submitted
- 2025-01-31: Planning Permission Granted
- 2028-01-31: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 14747. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.