slava.energy: UK renewable energy projects
Bristan, Pooley Hall Drive - Solar Pv Panels
REPD record 14826. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.67 MW
- Status
- Planning Permission Granted
- Operator
- Bristan Group Limited
- County
- Staffordshire
- Region
- West Midlands
- Country
- England
- Planning authority
- North Warwickshire
- Planning reference
- PAP/2023/0359
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-10-11
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-08-22: Planning Application Submitted
- 2023-10-05: Planning Permission Granted
- 2028-10-05: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 14826. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.