slava.energy: UK renewable energy projects
Kindeva Drug Delivery Limited, Derby Road - Solar Panels
REPD record 14841. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.88 MW
- Status
- Planning Permission Granted
- Operator
- Custom Solar Limited
- County
- Leicestershire
- Region
- East Midlands
- Country
- England
- Planning authority
- Charnwood
- Planning reference
- P/23/1530/2
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-10-05
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-09-04: Planning Application Submitted
- 2023-10-03: Planning Permission Granted
- 2026-10-03: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 14841. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.