Stanborough, Hatfield - Solar Array
REPD record 14878. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 10 MW
- Status
- Planning Permission Granted
- Operator
- J Reddington Limited
- County
- Hertfordshire
- Region
- Eastern
- Country
- England
- Planning authority
- Welwyn Hatfield
- Planning reference
- 6/2023/1802/MAJ
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-05-12
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-08-29: Planning Application Submitted
- 2024-09-16: Planning Permission Granted
- 2027-09-16: Planning Permission Expired