slava.energy: UK renewable energy projects
High Rigg Solar Farm - Solar Panels
REPD record 14881. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 30 MW
- Status
- Planning Permission Refused
- Operator
- Noventum Power Limited
- County
- Cumbria
- Region
- North West
- Country
- England
- Planning authority
- Westmorland and Furness
- Planning reference
- 2025/1267/FPA
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-04-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-07-15: Planning Application Submitted
- 2026-03-16: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 14881. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.