Barton Renewable Energy Plant
REPD record 149. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 20 MW
- Status
- Abandoned
- Operator
- Peel Energy
- County
- Greater Manchester
- Region
- North West
- Country
- England
- Planning authority
- Trafford
- Planning reference
- 76153/FULL/2010
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-06-20
Status history
Dated status events as published by REPD, release Q3 2026.
- 2010-12-07: Planning Application Submitted
- 2011-11-11: Planning Permission Refused
- 2013-05-16: Appeal Granted
- 2013-05-16: Planning Permission Expired
- 2013-05-16: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 149. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.