slava.energy: UK renewable energy projects
Waste & Recycling centre, Hornsey Street - Solar panels
REPD record 14910. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.43 MW
- Status
- Planning Permission Granted
- Operator
- Islington Council
- County
- London
- Region
- London
- Country
- England
- Planning authority
- Islington
- Planning reference
- P2023/2333/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-11-22
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-09-21: Planning Application Submitted
- 2023-11-16: Planning Permission Granted
- 2026-11-16: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 14910. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.