slava.energy: UK renewable energy projects
Bankhead, Arbirlot - Battery Energy Storage
REPD record 14985. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 49.9 MW
- Status
- Planning Permission Granted
- Operator
- Ecocel Energy Storage Limited
- County
- Angus
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Angus
- Planning reference
- 24/00178/FULM
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-10-28
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-03-25: Planning Application Submitted
- 2024-09-19: Planning Permission Granted
- 2027-09-19: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 14985. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.