slava.energy: UK renewable energy projects
Redcourt Farm
REPD record 1503. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 3.3 MW
- Status
- Operational
- Operator
- PS Renewables
- County
- Dyfed
- Region
- Wales
- Country
- Wales
- Planning authority
- Carmarthenshire
- Planning reference
- W/30060
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-05-18
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-05-01: Planning Application Submitted
- 2014-10-07: Planning Permission Granted
- 2015-01-15: Under Construction
- 2015-03-30: Operational
- 2019-10-07: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1503. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.