slava.energy: UK renewable energy projects
Bowerhouse Farm
REPD record 1518. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 8.3 MW
- Status
- Operational
- Operator
- KWTN Solar
- County
- Avon
- Region
- South West
- Country
- England
- Planning authority
- North Somerset
- Planning reference
- 14/P/1666/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-10-05
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-07-31: Planning Application Submitted
- 2014-10-30: Planning Permission Granted
- 2015-01-01: Under Construction
- 2015-03-29: Operational
- 2017-10-30: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1518. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.