Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 50 MW
- Status
- Revised
- Operator
- Newton Energi Limited
- County
- South Yorkshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- Doncaster
- Planning reference
- 23/01843/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-06-24
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-10-25: Planning Application Submitted
- 2023-12-12: Planning Permission Refused