Rectory Farm - Anaerobic Digestion Plant
REPD record 15259. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Anaerobic Digestion
- Capacity
- 7 MW
- Status
- Planning Permission Granted
- Operator
- Great Heck Green Energy Limited
- County
- Northamptonshire
- Region
- East Midlands
- Country
- England
- Planning authority
- North Northamptonshire
- Planning reference
- CCC/23/125/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-03-18
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-10-10: Planning Application Submitted
- 2025-03-11: Planning Permission Granted
- 2028-03-11: Planning Permission Expired