Goldborough Road, Hundleton - Battery Energy Storage
REPD record 15277. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 350 MW
- Status
- Planning Permission Granted
- Operator
- Pembroke Green Limited (Enso Energy and Cero Generation)
- County
- Pembrokeshire
- Region
- Wales
- Country
- Wales
- Planning authority
- Pembrokeshire
- Planning reference
- 24/0133/PA
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-07-28
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-05-10: Planning Application Submitted
- 2025-01-06: Planning Permission Granted
- 2030-01-06: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 15277. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.