Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 10 MW
- Status
- Revised
- Operator
- Green Energy UK Direct
- County
- Northamptonshire
- Region
- East Midlands
- Country
- England
- Planning authority
- West Northamptonshire
- Planning reference
- S/2014/0282/MAF
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2014-06-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-02-25: Planning Application Submitted
- 2014-05-07: Planning Application Withdrawn