David Lloyd Sports Centre, Darenth Road - Solar Photo Voltaic System
REPD record 15345. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.3 MW
- Status
- Planning Permission Granted
- Operator
- Centrica Business Solutions
- County
- Kent
- Region
- South East
- Country
- England
- Planning authority
- Dartford
- Planning reference
- 23/01365/P14J
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-01-19
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-11-21: Planning Application Submitted
- 2024-01-16: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 15345. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.