Corner Of Weeland Road, Lunn Lane - Battery Storage Facility
REPD record 15375. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 200 MW
- Status
- Planning Permission Granted
- Operator
- Newton Energi Limited
- County
- East Riding of Yorkshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- North Yorkshire
- Planning reference
- ZG2023/1179/FULM
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-09-11
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-11-02: Planning Application Submitted
- 2025-07-31: Planning Permission Granted
- 2028-07-31: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 15375. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.