slava.energy: UK renewable energy projects
Rushett Lane - Battery Storage System
REPD record 15398. Status: Appeal Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 30 MW
- Status
- Appeal Granted
- Operator
- Enso Energy
- County
- Surrey
- Region
- South East
- Country
- England
- Planning authority
- Epsom and Ewell
- Planning reference
- 24/00756/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-05-06
Status history
Dated status events as published by REPD, release Q3 2026.
- 2016-04-03: Planning Permission Expired
- 2024-04-16: Planning Application Submitted
- 2024-07-16: Planning Permission Refused
- 2024-11-25: Appeal Lodged
- 2025-04-03: Appeal Granted
- 2025-04-03: Planning Permission Granted
Open this area on the map