slava.energy: UK renewable energy projects
Killen Farm, Killen - Biomass Boiler
REPD record 15471. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 0.18 MW
- Status
- Planning Permission Granted
- Operator
- Glen Farrow UK Limited
- County
- Highland
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Highland
- Planning reference
- 23/05309/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-04-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-02-27: Planning Permission Expired
- 2023-11-23: Planning Application Submitted
- 2024-02-27: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 15471. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.