First Steps Nursery, Waterloo Road - Solar Panels
REPD record 15508. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.3 MW
- Status
- Planning Permission Granted
- Operator
- Solar Options For Schools Limited
- County
- West Midlands
- Region
- West Midlands
- Country
- England
- Planning authority
- Sandwell
- Planning reference
- PD/23/02588
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-02-15
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-02-07: Planning Permission Expired
- 2023-12-19: Planning Application Submitted
- 2024-02-07: Planning Permission Granted