slava.energy: UK renewable energy projects

Cruachan Upgrade Project (Unis 3 & 4)

REPD record 15543. Status: Planning Permission Granted.

Facts

As published by REPD, release Q3 2026.

Technology
Pumped Storage Hydroelectricity
Capacity
40 MW
Status
Planning Permission Granted
Operator
Drax Power Limited
County
Strathclyde
Region
Scotland
Country
Scotland
Planning authority
Scottish Government (S36)
Planning reference
ECU00004537
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2024-01-09

Status history

Dated status events as published by REPD, release Q3 2026.

Open this area on the map

Other REPD records on the same site

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 15543. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.