slava.energy: UK renewable energy projects
Farnborough International Exhibition Centre, Etps Road - Solar Panels
REPD record 15581. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1.15 MW
- Status
- Under Construction
- Operator
- Farnborough International Limited
- County
- Hampshire
- Region
- South East
- Country
- England
- Planning authority
- Rushmoor
- Planning reference
- 23/00885/FULPP
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-02-19
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-12-04: Under Construction
- 2023-12-20: Planning Application Submitted
- 2024-02-15: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 15581. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.