Chimmens Solar Farm
REPD record 15628. Status: Appeal Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- not held by REPD
- Status
- Appeal Granted
- Operator
- RES Limited
- County
- Kent
- Region
- South East
- Country
- England
- Planning authority
- Sevenoaks
- Planning reference
- 23/03181/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-08-05
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-12-19: Planning Application Submitted
- 2024-07-23: Planning Permission Refused
- 2025-07-23: Appeal Granted
- 2025-07-23: Planning Permission Granted
Open this area on the map