slava.energy: UK renewable energy projects
Snapewood Solar Farm
REPD record 15697. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 10 MW
- Status
- Planning Permission Granted
- Operator
- ABEI Energy
- County
- Lancashire
- Region
- North West
- Country
- England
- Planning authority
- Wyre
- Planning reference
- 25/00294/LMAJ
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-05-08
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-04-25: Planning Application Submitted
- 2026-03-05: Planning Permission Granted
- 2029-03-05: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 15697. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.