slava.energy: UK renewable energy projects
Longannet
REPD record 157. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 25 MW
- Status
- Abandoned
- Operator
- Scottish Power Renewables
- County
- Fife
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Fife
- Planning reference
- 07/01283/WEIA
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-01-11
Status history
Dated status events as published by REPD, release Q3 2026.
- 2007-04-16: Planning Application Submitted
- 2008-08-22: Planning Permission Granted
Open this area on the map