Sandholme Iron Works, Halifax Road - Solar Panels
REPD record 15704. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.83 MW
- Status
- Planning Permission Granted
- Operator
- Weir Minerals
- County
- West Yorkshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- Calderdale
- Planning reference
- 23/56018/CLA14J
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-02-29
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-02-20: Planning Permission Expired
- 2024-01-02: Planning Application Submitted
- 2024-02-20: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 15704. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.