Oving Solar Farm
REPD record 1571. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Operational
- Operator
- Vogt Solar
- County
- West Sussex
- Region
- South East
- Country
- England
- Planning authority
- Chichester
- Planning reference
- 11/00738/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2012-12-06
Status history
Dated status events as published by REPD, release Q3 2026.
- 2011-02-21: Planning Application Submitted
- 2011-05-03: Planning Permission Expired
- 2011-05-03: Planning Permission Granted
- 2012-05-04: Under Construction
- 2012-08-14: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1571. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.