Potterne Park Farm, Potterne - Solar Farm
REPD record 15715. Status: Appeal Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 49.9 MW
- Status
- Appeal Granted
- Operator
- Potterne Solar Project Limited
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Wiltshire
- Planning reference
- PL/2023/10332
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-05-19
Status history
Dated status events as published by REPD, release Q3 2026.
- 2023-12-20: Planning Application Submitted
- 2025-07-03: Planning Permission Refused
- 2026-04-20: Appeal Granted
- 2026-04-20: Planning Permission Granted
- 2029-04-20: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 15715. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.