North Norfolk Business Centre Solar Park
REPD record 1590. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 11 MW
- Status
- Operational
- Operator
- NESF (formerly Lumicity) & Next Energy
- County
- Norfolk
- Region
- Eastern
- Country
- England
- Planning authority
- North Norfolk
- Planning reference
- PF/12/0816
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-03-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-07-30: Planning Application Submitted
- 2012-11-16: Planning Permission Granted
- 2013-08-30: Under Construction
- 2013-11-16: Planning Permission Expired
- 2014-02-28: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1590. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.