slava.energy: UK renewable energy projects
Pentylands Farm
REPD record 1593. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 19 MW
- Status
- Operational
- Operator
- Moser Baer
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Swindon
- Planning reference
- S/12/1094
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2014-04-30
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-08-08: Planning Application Submitted
- 2012-11-15: Planning Permission Granted
- 2013-09-30: Under Construction
- 2014-03-31: Operational
- 2018-11-15: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1593. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.