Progress Way, Marston Green - Solar Array
REPD record 15939. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.25 MW
- Status
- Planning Permission Granted
- Operator
- Prologis UK Limited
- County
- West Midlands
- Region
- West Midlands
- Country
- England
- Planning authority
- Solihull
- Planning reference
- PL/2024/00268/PNSVP
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-04-03
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-02-13: Planning Application Submitted
- 2024-03-28: Planning Permission Granted