Reality Energy Centre, Immingham
REPD record 160. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 49.9 MW
- Status
- Planning Permission Expired
- Operator
- Real Ventures
- County
- Humberside
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- North East Lincolnshire
- Planning reference
- DC/999/11/IMM
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-11-26
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-01-12: Planning Application Submitted
- 2012-04-12: Planning Permission Granted
- 2015-04-12: Planning Permission Expired