slava.energy: UK renewable energy projects

Hacheston Solar farm

REPD record 1602. Status: Appeal Refused.

Facts

As published by REPD, release Q3 2026.

Technology
Solar Photovoltaics
Capacity
25 MW
Status
Appeal Refused
Operator
Hive Energy
County
Suffolk
Region
Eastern
Country
England
Planning authority
East Suffolk
Planning reference
C/12/1899
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2014-06-02

Status history

Dated status events as published by REPD, release Q3 2026.

Open this area on the map

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1602. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.