Camilla Battery Storage
REPD record 16075. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 49.99 MW
- Status
- Operational
- Operator
- NextEnergy Solar Fund & Eelpower Limited
- County
- Fife
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Fife
- Planning reference
- 20/01765/ARC
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-03-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-08-26: Planning Application Submitted
- 2022-10-22: Planning Permission Granted
- 2023-10-01: Under Construction
- 2024-03-20: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 16075. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.