High Barnes Farm, Coal Lane - Battery Storage
REPD record 16082. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 25 MW
- Status
- Planning Permission Granted
- Operator
- Enviromena Project Management UK Limited
- County
- Cleveland
- Region
- North East
- Country
- England
- Planning authority
- Hartlepool
- Planning reference
- H/2024/0180
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-05-19
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-08-06: Planning Application Submitted
- 2025-05-28: Planning Permission Granted
- 2027-05-28: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 16082. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.