slava.energy: UK renewable energy projects
HENDRA HOLIDAY PARK SOLAR FARM
REPD record 1609. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1.2 MW
- Status
- Operational
- Operator
- Hendra Holiday Park
- County
- Cornwall
- Region
- South West
- Country
- England
- Planning authority
- Cornwall
- Planning reference
- PA11/03163
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2013-10-08
Status history
Dated status events as published by REPD, release Q3 2026.
- 2011-04-14: Planning Application Submitted
- 2011-07-14: Planning Permission Granted
- 2011-08-07: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1609. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.