EASTACOMBE SOLAR FARM
REPD record 1610. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 3.6 MW
- Status
- Operational
- Operator
- The Green Company
- County
- Devon
- Region
- South West
- Country
- England
- Planning authority
- Torridge
- Planning reference
- 1/0208/2011/FULM
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2012-10-23
Status history
Dated status events as published by REPD, release Q3 2026.
- 2011-04-11: Planning Application Submitted
- 2011-06-30: Planning Permission Granted
- 2012-05-01: Under Construction
- 2012-07-01: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1610. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.