slava.energy: UK renewable energy projects

Tick Fen Farm, Puddock Road - Wind Turbine

REPD record 16105. Status: Planning Permission Granted.

Facts

As published by REPD, release Q3 2026.

Technology
Wind Onshore
Capacity
0.5 MW
Status
Planning Permission Granted
Operator
Whittome Farms
County
Cambridgeshire
Region
Eastern
Country
England
Planning authority
Huntingdonshire
Planning reference
24/00311/FUL
Turbines
1
Turbine size
0.5 MW
Record last updated in REPD
2024-07-09

Status history

Dated status events as published by REPD, release Q3 2026.

Position not held by REPD.

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 16105. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.