Mugdock Water Treatment Works - Solar panels
REPD record 16120. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.75 MW
- Status
- Operational
- Operator
- Scottish Water National Operations Control Centre
- County
- Strathclyde
- Region
- Scotland
- Country
- Scotland
- Planning authority
- East Dunbartonshire
- Planning reference
- TP/ED/24/0084
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-07-28
Status history
Dated status events as published by REPD, release Q3 2026.
- 2021-05-16: Planning Permission Expired
- 2024-03-19: Planning Application Submitted
- 2024-05-16: Planning Permission Granted
- 2025-06-01: Operational
Open this area on the map