slava.energy: UK renewable energy projects
Town Farm, Blackawton - Battery Storage System
REPD record 16229. Status: Planning Application Withdrawn.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 3 MW
- Status
- Planning Application Withdrawn
- Operator
- Aldustria Energy Storage
- County
- Devon
- Region
- South West
- Country
- England
- Planning authority
- South Hams
- Planning reference
- 0697/24/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-05-31
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-04-03: Planning Application Submitted
- 2024-05-13: Planning Application Withdrawn
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 16229. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.