slava.energy: UK renewable energy projects
Cummins Turbo Technologies, St Andrews Road - Solar panels
REPD record 16401. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.45 MW
- Status
- Planning Permission Granted
- Operator
- Cummins Turbo Technologies
- County
- West Yorkshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- Kirklees
- Planning reference
- 2024/CLASS J/91360/W
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-07-16
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-05-14: Planning Application Submitted
- 2024-07-03: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 16401. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.