slava.energy: UK renewable energy projects
Steventon Road - Battery Energy Storage
REPD record 16590. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 23 MW
- Status
- Planning Permission Granted
- Operator
- Greenfield Company
- County
- Shropshire
- Region
- West Midlands
- Country
- England
- Planning authority
- Shropshire
- Planning reference
- 24/02223/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-09-09
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-06-21: Planning Application Submitted
- 2024-08-30: Planning Permission Granted
- 2027-08-30: Planning Permission Expired