slava.energy: UK renewable energy projects
Woodcock Solar Farm, Sweeming Lane - Battery Energy Storage
REPD record 16640. Status: Planning Application Submitted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 4.7 MW
- Status
- Planning Application Submitted
- Operator
- AEUK Solar Project IX
- County
- West Yorkshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- North Yorkshire
- Planning reference
- ZG2024/1322/FULM
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-02-21
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-01-27: Planning Application Submitted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 16640. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.