slava.energy: UK renewable energy projects

Springfield Farm, Weeland Road - Battery Energy Storage Facility

REPD record 16644. Status: Planning Permission Granted.

Facts

As published by REPD, release Q3 2026.

Technology
Battery
Capacity
240 MW
Status
Planning Permission Granted
Operator
Newton Energi Limited
County
East Riding of Yorkshire
Region
Yorkshire and Humber
Country
England
Planning authority
North Yorkshire
Planning reference
ZG2024/0549/FULM
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2025-06-09

Status history

Dated status events as published by REPD, release Q3 2026.

Open this area on the map

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 16644. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.