slava.energy: UK renewable energy projects
Stenson Lane - Battery Energy Storage System
REPD record 16675. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 400 MW
- Status
- Planning Permission Granted
- Operator
- Innova Renewables
- County
- Derbyshire
- Region
- East Midlands
- Country
- England
- Planning authority
- South Derbyshire
- Planning reference
- DMPA/2024/0586
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-12-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-05-16: Planning Application Submitted
- 2025-10-27: Appeal Granted
- 2025-10-27: Planning Permission Granted
- 2028-10-27: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 16675. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.