slava.energy: UK renewable energy projects
Tesco Distribution Centre, Goole
REPD record 167. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 5 MW
- Status
- Abandoned
- Operator
- Tesco
- County
- Humberside
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- East Riding of Yorkshire
- Planning reference
- 11/02623/STPLFE
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-12-08
Status history
Dated status events as published by REPD, release Q3 2026.
- 2003-07-17: Planning Permission Expired
- 2007-08-22: Planning Application Submitted
- 2008-07-17: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 167. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.