Ryston Estate Solar Park
REPD record 1672. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4.8 MW
- Status
- Operational
- Operator
- Lightsource Renewable Energy
- County
- Norfolk
- Region
- Eastern
- Country
- England
- Planning authority
- King's Lynn and West Norfolk
- Planning reference
- 13/00692/FM
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-08-03
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-05-14: Planning Application Submitted
- 2013-08-13: Planning Permission Granted
- 2014-08-06: Under Construction
- 2015-05-07: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1672. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.