Langer Lane Solar Farm
REPD record 16745. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 7.5 MW
- Status
- Planning Permission Granted
- Operator
- Ethical Power Development Limited
- County
- Derbyshire
- Region
- East Midlands
- Country
- England
- Planning authority
- North East Derbyshire
- Planning reference
- 24/00506/MFL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-02-19
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-07-12: Planning Application Submitted
- 2025-04-17: Planning Permission Granted
- 2028-04-17: Planning Permission Expired