slava.energy: UK renewable energy projects
Clayhill Farm, Greenfield Road - Battery Energy Storage
REPD record 16782. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 20 MW
- Status
- Planning Permission Granted
- Operator
- Conrad Energy (Developments) Limited
- County
- Bedfordshire
- Region
- Eastern
- Country
- England
- Planning authority
- Central Bedfordshire
- Planning reference
- CB/24/02825/FULL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-01-14
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-10-01: Planning Application Submitted
- 2024-12-18: Planning Permission Granted
- 2027-12-18: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 16782. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.