slava.energy: UK renewable energy projects
Whisby Quarry, Eagle Road - Solar Array
REPD record 16797. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 18 MW
- Status
- Planning Permission Granted
- Operator
- Conrad Energy
- County
- Lincolnshire
- Region
- East Midlands
- Country
- England
- Planning authority
- North Kesteven
- Planning reference
- PL/0130/24
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-11-07
Status history
Dated status events as published by REPD, release Q3 2026.
- 2025-01-21: Planning Application Submitted
- 2025-09-17: Planning Permission Granted
- 2028-09-17: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 16797. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.