slava.energy: UK renewable energy projects
New Tyning Farm
REPD record 1684. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5.8 MW
- Status
- Appeal Refused
- Operator
- INRG Solar
- County
- Somerset
- Region
- South West
- Country
- England
- Planning authority
- Somerset
- Planning reference
- 2013/1356
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2014-11-25
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-06-29: Planning Application Submitted
- 2014-01-16: Planning Permission Refused
- 2014-03-17: Appeal Lodged
- 2014-10-01: Appeal Refused
Open this area on the map